File #: 22-1602    Version: 1 Name:
Type: Presentation Status: Filed
File created: 12/9/2022 In control: Finance Committee
On agenda: 12/12/2022 Final action: 12/12/2022
Title: Change Orders #6, #7 and #8 to Sabel Mechanical contract as part of the 2021 Secondary Clarifier Drive Removal, Rebuild, and Reinstallation Project totaling $5,546.88 resulting in a decrease in contingency from $39,060.06 to $33,513.18
Attachments: 1. 221209_Finance Memo SecondaryClariferDrive_Sabel_Change Orders No6-8.pdf

Title

Change Orders #6, #7 and #8 to Sabel Mechanical contract as part of the 2021 Secondary Clarifier Drive Removal, Rebuild, and Reinstallation Project totaling $5,546.88 resulting in a decrease in contingency from $39,060.06 to $33,513.18