Title
Contract 15-12 was awarded to Boldt Construction "Houdini Plaza Construction" $1,220,268 with a contingency of $61,013.44. Five change orders were issued totaling $24,064.80. Final contract amount is $1,244,332.80 with remaining contingency of $36,948.64. Payments issued to date totals $1,182,116.16. Request to issue the final contract payment of $62,616.64.