Title: Change Orders #2, #3, and #4 to Staab Construction contract as part of the AWWTP Phase 2 Belt Filter Press Equipment Upgrade Project totalling $84,851 resulting in a decrease in contingency from $185,662 to $100,811
Attachments: 1. 250605_Finance Memo_Phase 2 BFP Change Orders 2- 4_Staab.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Change Orders #2, #3, and #4 to Staab Construction contract as part of the AWWTP Phase 2 Belt Filter Press Equipment Upgrade Project totalling $84,851 resulting in a decrease in contingency from $185,662 to $100,811