Title: Contract 6-13 was awarded to SAK Construction, LLC for $843,983.50 with a contingency of $56,016.50 for sanitary and storm sewer CIP.  No change orders were approved. Final contract amount is $843,943.50 without a contingency.  Payment issued to date totals $792,303.31. Request to issue the final contract payment of $41,700.19.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
Contract 6-13 was awarded to SAK Construction, LLC for $843,983.50 with a contingency of $56,016.50 for sanitary and storm sewer CIP.  No change orders were approved. Final contract amount is $843,943.50 without a contingency.  Payment issued to date totals $792,303.31. Request to issue the final contract payment of $41,700.19.