Title:
|
Contract 48-24 was awarded to Rohde Brothers for $1,612,000 with a contingency of $241,800 for the WWTP Sludge Piping & Digester Heat Exchange. Change orders were approved totaling $210,689. Final contract amount is $1,822,689 with a contingency of $31,111. Payments issued to date total $1,777,121.77. Request final payment of $45,567.23.
|