Title:
|
Contract 160-23 was awarded to Rohde Brothers for $177,700 with a contingency of $40,014 for Water Air Compressor. Change orders were approved totaling $1,256. Final contract amount is $178,956. Payments issued to date total $171,949. Request final payment of $7,007.00.
|