| Title: | Contract 1-18 was awarded to Kruczek Construction, Inc for $1,477,778 with a contingency of $73,889 for Telulah Avenue Sewer/Water Construction project.  Change orders were approved totaling $19,500. Final contract amount is $1,497,278 with a contingency of $54,389.  Payments issued to date total $1,436,892.39.  Request final payment of $39,817.94 |