File #: 23-1092    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 9/8/2023 In control: Finance Committee
On agenda: 9/11/2023 Final action: 9/20/2023
Title: Request to approve Change Order #3 to contract 72-22 for Unit H-21 Redundant Raw Water Line to increase for unanticipated site conditions in the amount of $200,000 resulting in a decrease to contingency from $444,549.71 to $244,549.71. No change to overall contract amount.
Attachments: 1. H-21 Change Order 3 memo.pdf, 2. Unit H-21 Change Order No 3.pdf

Title

Request to approve Change Order #3 to contract 72-22 for Unit H-21 Redundant Raw Water Line to increase for unanticipated site conditions in the amount of $200,000 resulting in a decrease to contingency from $444,549.71 to $244,549.71. No change to overall contract amount.