Title: Contract 13-14 was awarded to Johnson and Jonet, “Library Boiler Replacement” $102,100 with a contingency of $10,000. One change order was issued totaling $2,319.62. Final contract amount is $104,419.62 with remaining contingency of $7,680.38. Payments issued to date totals $99,198.62. Request to issue the final contract payment of $5,221.00
Attachments: 1. 2014 Library Boiler Final Pymt.pdf
Title
Contract 13-14 was awarded to Johnson and Jonet, "Library Boiler Replacement" $102,100 with a contingency of $10,000.  One change order was issued totaling $2,319.62.  Final contract amount is $104,419.62 with remaining contingency of $7,680.38.  Payments issued to date totals $99,198.62.  Request to issue the final contract payment of $5,221.00