Title: Approve Contract Amendment #1 to McMahon for Phase II Solids Dewatering Equipment Upgrades for additional design and construction management services in the amount of $26,900 increasing the contract amount from $162,000 to $188,900
Attachments: 1. 240501_Ph2-BFP_McMahon_ContractAmend_no1_memo.pdf

Title

Approve Contract Amendment #1 to McMahon for Phase II Solids Dewatering Equipment Upgrades for additional design and construction management services in the amount of $26,900 increasing the contract amount from $162,000 to $188,900