File #: 22-1599    Version: 1 Name:
Type: Presentation Status: Filed
File created: 12/8/2022 In control: Finance Committee
On agenda: 12/12/2022 Final action: 12/12/2022
Title: Contract Change Order No. 1 to contract 72-22, Unit H-21 Redundant Raw Water Line for a change at the connection point at the lake pumping station requiring a special fitting to be fabricated in the amount of $25,000 resulting in a reduction in contingency from $500,000 to $475,000. Overall contract amount remains unchanged.
Attachments: 1. Unit H-21 Change Order No. 1.pdf

Title

Contract Change Order No. 1 to contract 72-22, Unit H-21 Redundant Raw Water Line for a change at the connection point at the lake pumping station requiring a special fitting to be fabricated in the amount of $25,000 resulting in a reduction in contingency from $500,000 to $475,000. Overall contract amount remains unchanged.