Contract 126-20 was awarded to Miron Construction Co. for the 2020 Fire Station #1 Bathroom Remodeling project in the amount of $182,257 with a contingency of $18,226. Three change orders were issued that total $15,779.27 to make additional wall and ceiling repairs, additional epoxy floors, and fire alarm modifications. Payments to date total $193,085.36. Request to issue the final contract payment of $4,950.91
|