Skip to main content
File #: 25-0851    Version: 1 Name:
Type: Report Action Item Status: Action Item
File created: 7/17/2025 In control: Finance Committee
On agenda: 7/21/2025 Final action: 7/21/2025
Title: Change Orders #2 and #3 to Sabel Mechanical as part of the AWWTP Mix Liquor Channel Blower Replacement Project totaling $18,581.61 resulting in a decrease in contingency from $43,856.81 to $25,275.20.
Attachments: 1. 250710_FinanceMemo_AWWTP MLChannelBlower_ChangeOrders2-3.pdf

Title

Change Orders #2 and #3 to Sabel Mechanical as part of the AWWTP Mix Liquor Channel Blower Replacement Project totaling $18,581.61 resulting in a decrease in contingency from $43,856.81 to $25,275.20.