File #: 24-0464    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 4/17/2024 In control: Utilities Committee
On agenda: 4/23/2024 Final action: 5/1/2024
Title: Approval of Sole Source Engineering Services Contract to McMahon as part of 2024 Primary Clarifiers #1 through #4 Rehabilitation Project in the amount of $57,900 with a 15% contingency of $8,685 for a Project Total not to exceed $66,585.
Attachments: 1. 240421_UCMemo(revised)_Sole Source Contract_McMahon_PrimClarifer1-4.pdf

Title

Approval of Sole Source Engineering Services Contract to McMahon as part of 2024 Primary Clarifiers #1 through #4 Rehabilitation Project in the amount of $57,900 with a 15% contingency of $8,685 for a Project Total not to exceed $66,585.