Title:
|
Contract 46-24 was awarded to Carl Bowers & Sons Construction Company for $2,301,282.52 with a contingency of $65,000.00 for G-24 Southpoint Commerce Center Sewer and Water, Grade and Gravel. Change orders were approved totaling $55,000.00. Final contract amount is $2,356,282.52 with a contingency of $10,000.00. Payments issued to date total $2,122,321.35. Request final payment of $230,574.20.
|