File #: 17-577    Version: 1 Name:
Type: Report Action Item Status: Passed
File created: 4/20/2017 In control: Finance Committee
On agenda: 4/25/2017 Final action: 5/3/2017
Title: Request to approve Contract Amendment/Change Order No. 1 to contract 73-16 for Unit Y-16 Arbutus Park Stormwater Lift Station Reconstruction to increase for the addition of retaining wall reconstruction to the scope of work in the amount of $45,925.00 resulting in an increase to contingency from $21,377.50 to $25,877.50. Overall contract increased from $235,152.50 to $285,577.50.
Attachments: 1. Unit Y-16 Contract Amendment-Change Order No.1.pdf

Title

Request to approve Contract Amendment/Change Order No. 1 to contract 73-16 for Unit Y-16 Arbutus Park Stormwater Lift Station Reconstruction to increase for the addition of retaining wall reconstruction to the scope of work in the amount of $45,925.00 resulting in an increase to contingency from $21,377.50 to $25,877.50.  Overall contract increased from $235,152.50 to $285,577.50.