Title:
|
Contract 159-23 was awarded to August Winter & Sons for $573,355 with a contingency of $57,336 for Grit System & Raw Sludge Pump Replacement. Change orders were approved totaling $35,009. Final contract amount is $608,364 with a contingency of $22,327. Payments issued to date total $592,964.67. Request final payment of $15,399.33.
|